Various Locations Sidewalk Repairs
| Project Description: | Repair Sidewalk, Curb, Gutter & Driveway Aprons |
| Section of Town or address: | Upham Place,NW Lawyers Road,NW Courthouse Road,SW Heritage Lane,NW Colony Court,NW & other various locations |
| Project Manager: | Matthew Randall |
| Design Consultant: | |
| Design % Complete: | |
| Project Budget: | $210,000.00 |
| Engineering Estimate: | N/A |
| Construction Manager: | Glenn Cornell |
| Construction Firm: | Sagres Construction Corp. |
| Construction Start Date: | September 9, 2008 |
| Original Completion Date: | N/A |
| Revised Completion Date: | N/A |
| Original Bid Amount: | N/A |
| Change Order Value to Date: | N/A |
| Design Comments: | N/A |
| Construction Comments: | N/A |
| Updated: | November 2008 |
|
|
|